Section 278 works to facilitate access onto a 74-acre site for proposed housing and retail development on the outskirts of Haverfordwest. Work included: Creation of a new roundabout on the…
Design and Build project for a new parking facility for 170 articulated lorries. The site is located on Parc Cybi industrial park on the outskirts of Holyhead, close to the…
The 50:50 joint venture between Jones Bros and Balfour Beatty saw the construction of a 5.2km carriageway. The project was constructed through SSSIs and AONB, predominantly on green field land…
Bulk excavation and infrastructure work included: Construction of 1,750m of a 7.3m wide carriageway Construction of four new roundabouts and modification of existing A55 slipway roundabout Street lighting, footpaths, fencing…
Jones Bros designed and constructed a renewable energy education centre at Aberthaw Power Station near Barry, South Wales. A number of sustainable building technologies were installed in this bespoke project.…
Work was carried out on the A55 trunk road between Llanddulas and Pensarn – the only remaining section of the A55 that failed to meet carriageway standards. The scheme increased…
Failure of several rock anchors on the north face of the rock cutting was discovered during routine inspection. For safety reasons the road was closed and traffic was diverted. Cutting…
Prior to work starting on the first phase of infrastructure works to open up the 90-acre site for development, a full archaeological investigation was carried out. Jones Bros worked closely…
Work involved large-scale earth and rock moving and high quality track surfacing, as well as quarrying and aggregate crushing/processing. In total, 350,000 cubic metres of soil and rock were stripped…