Running for four years to 2021, Jones Bros successfully undertook £43m of work for the waste management company, delivered in-house by one of the largest plant fleets in the UK.…
Activity at the landfill site in Markham Vale, Chesterfield, was split into three areas: Leachate reception area Permanent capping Cell 4a, 4b, and asbestos cell extension. Works included: Constructing a…
Construction of material recycling facility for the treatment of non-hazardous commercial and industrial waste. Developed on the client’s existing landfill and composting site, the MRF has the capacity to process…
The project was primarily to enable existing gas wells to continue extracting gas, whilst having the ability to incorporate pneumatic pumps to assist with leachate control. Works included: Installation of…
Cell construction works included: 300,000m3 of bulk earthworks, de-watering of sands and gravels Under cell drainage for progression of earthworks 15,000m3 of sand excavation for quarrying operations 25,000m2 engineered clay…
Capping and restoration works to landfill cell, including temporary capping of a recently completed area, and construction of new landfill cell. Works included: Regulating geomembrane lining of completed area of…