Balance of plant civils and electrical infrastructure for 10 Repower 2.0MW turbines.
Major activities included:
- Design and construction of 7km of site access tracks
- Construction of concrete turbine and crane pad foundations using locally sourced steel and concrete (all turbine bases pile driven)
- Construction of substation building using local labour
- 5.5km of on-site cable trenching and cable laying
- Construction of new Section 278 approved site entrance off public highway
- Construction of a new steel and timber deck bridge to enable crossing of near drain
- Design and construction of on-site drainage to comply with drainage board and landowner requirements
- Electrical installation by specialist subcontractor
- Landscaping and reinstatement of all site tracks and crane pads