Cheshire Green Employment Park

Cheshire Green Employment Park

Client:
Contract value:
£828k
Contract date:
June 2017 - December 2017
Capabilities:
Highways Highways project 2024

Split into two phases, which were classified as the Industrial Estate (phase one) and the Employment Park (phase two), activity focused on the construction of a roundabout and spine road.

Works included:

  • 50,000m3 of cut to stockpile, with no material being removed from site
  • New infrastructure connections which required close management
  • Primary substation and compound for Scottish Power
  • 2km of surface water and foul drainage, including two pumping stations and tubosider attenuation
  • 1km of access road
  • 3km rising main