King’s Dyke level crossing scheme hits key milestone early3rd Dec 2020

A key milestone has been reached two months ahead of schedule on the £32m King’s Dyke transport scheme in Whittlesey.

Jones Bros Civil Engineering UK has completed the first section of earthworks to the south of the railway line at the much-anticipated King’s Dyke level crossing project.

The early delivery of the embankment, which the road will sit on, removes risk from adverse weather in the winter months delaying the works and the overall programme timetable.

Jones Bros was appointed by Cambridgeshire County Council and started on site in July.

The civil engineering contractor will now turn its attention to constructing the two main structures, the bridge over the railway line and Star Pit, as well as the underpass, which will continue the private access to Star Pit.

In addition, the team will start the construction of the embankment on the north side of the railway line using the material that has been stockpiled in advance of the works.

Section one in October 2020

The scheme, which includes a new road and bridge over the Ely to Peterborough railway line, is due open to traffic by December 2022. The level crossing will be permanently closed as part of the scheme.

Jones Bros construction manager Rhydian Hafal said: “Completing this element of the project two months early is a huge success for the workforce.

“The winter months always come with a risk of bad weather that can delay projects, so for the team to achieve this milestone is fantastic.

“As part of the ground improvement works, which included installing 9,000 vertical drains, the embankment will now enter a six-month settlement period which we will review via the ground settlement monitoring points installed.

“Our focus is now on building the structures as well as progressing the earthworks to the north of the railway to construct this section of the embankment.”

Section one back in August 2020

Cambridgeshire County Council Highways and Transport Committee Chairman Cllr Ian Bates said: “Achieving this key milestone in the project two months early and ahead of winter is great news.

“Jones Bros are progressing well with this much-needed project and remain on track for the new road and bridge to open to traffic by December 2022.”

Mayor James Palmer added: “Glad to hear that the phase one earthworks have finished 2 months earlier than anticipated. It’s important that these projects are as time and resource-efficient as possible, and I hope that the rest of the project will carry on in the same vein.”

Cambridgeshire County Council and Jones Bros have been working hard to manage the coronavirus situation and all construction activity complies with the Government’s COVID-19 restrictions and national construction site operating procedures.

For more information about King’s Dyke visit our website at www.cambridgeshire.gov.uk/kings-dyke

A time-lapse video of the work so far is available to watch here

Established in the 1950s, Jones Bros’ leadership team consists of members of the second and third generations of the founding family. It employs close to 500 people.

The company is currently working on contracts in various sectors including highwaysflood and marine defencewaste management and renewable energy around the UK.

The company runs an award-winning apprenticeship scheme, which has produced more than 40 per cent of its current workforce, with many of its senior managers having started out as apprentices or in a trainee role.  It has recruited more than 100 apprentices during the past three years.

For more information visit www.jones-bros.com 