Parc Cybi Industrial Estate

Client:
Welsh Government
Contract Value:
£8.3m
Contract Date:
2007 – 2008
Location:
Parc Cybi

Bulk excavation and infrastructure work included:

  • Construction of 1,750m of a 7.3m wide carriageway
  • Construction of four new roundabouts and modification of existing A55 slipway roundabout
  • Street lighting, footpaths, fencing and random stone walling
  • Highway and surface water drainage, including drainage swales and gravity foul sewers
  • New reinforced earth and in situ concrete underpass, designed and constructed by Jones Bros
  • Landscaping
  • Service diversions

All work was carried out under strict archaeological constraints due to the proximity of ancient national monuments.

Also in this section

Jones Bros is one of the UK’s leading civil engineering contractors with a wealth of experience across a broad range of sectors.
© 2026 Jones Bros. All rights reserved.
There are many variations of passages of Lorem Ipsum available, but the majority have suffered alteration in some form.

Let’s Work Together